9-23-19 fdl weekly construction schedule

East Cotton Street from North Park Avenue to McKinley Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
September 23 rd to September 27 th : The grading contractor will be excavating terraces with the landscape contractor placing, seeding and mulching topsoil.
Traffic Impacts: East Cotton Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
McKinley Street from Rose Avenue to Stow Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
September 23 rd to September 27 th : The grading contractor will be excavating terraces with the landscape contractor placing, seeding and mulching topsoil.
Traffic Impacts: Traffic Impacts: McKinley Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Stow Street from McKinley Street to Roosevelt Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
September 23 rd to September 27 th : The grading contractor will be excavating terraces with the landscape contractor placing, seeding and mulching topsoil.
Traffic Impacts: Stow Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Marquette Street from Arndt Street to McWilliams Street
Schedule: July 2019 through October 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
September 23 rd to September 27 th : The utility contractor will finish installing storm sewer main, catch basins and sanitary sewer main/laterals.
Traffic Impacts: Marquette Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Arndt Street Bridge Replacement, Arndt Street between Satterlee Street and Lincoln Avenue
Schedule: June 2019 through October 2019
Description: The project includes the replacement of the Arndt Street Bridge over the West Branch of the Fond Du Lac River. This project is a partnership between the City of Fond du Lac and the Wisconsin Department  of Transportation (DOT).
September 23 rd to September 27 th : Contractor will continue forming and pouring the wingwalls, sidewalks and parapets on the new bridge deck.
Traffic Impacts: Arndt Street between Lincoln Ave. and Satterlee Street is closed to thru-traffic. Boat traffic under the structure will be restricted at time as work progresses.
County Road V from Pioneer Road to Fond du Lac Avenue Pioneer Road from Sherwood Boulevard to Wedgewood Road
Schedule: April 2019 through end of November 2019
Description of work: The project includes reconstruction of the water main and services and partnership with Fond du Lac County for new storm sewer, street, pedestrian trail, and lighting.
September 13 th to September 20 th : Fond du Lac County Highway Dept continues work on storm sewer installation and common excavation on CTH V from Tap Street north.  Electrical Contractor continues to install conduit and bases on CTH V from CTH VV north to Mequon Avenue.  CTH VV segment, the roundabout and CTH V south of the intersection have first layer of asphalt installed along with all curbs and side walk areas backfilled with top soil.   Concrete contractor scheduled to move back in week of 23th to continue pouring islands, truck aprons and start setting and installation of the new curb and gutter, sidewalk, and driveways along CTH V north of CTH  VV Pioneer  Road segment up to Tap Street.
Traffic impacts: County Road V from Fond du Lac Avenue and Pioneer Road is closed to through traffic. Additionally,  Pioneer Road from Sherwood Blvd to Wedgewood Lane is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Project Detour: North on Fond du Lac Avenue to South on Martin Avenue to west on Pioneer Road. WIS 23 Resurfacing
Location/Limits: WIS 23 from Town line Road to County VVV Fond du Lac County.
Length of Project: 1.9 miles
Schedule: September 9, 2019 to late November 2019
Description of work: This project will resurface WIS 23 in the project limits and add a left-turn and right-turn lane at the intersection of WIS 23 and Esterbrook Drive. Slotted left-turn lanes will be added at the WIS 23/County VVV intersection along with new signal upgrades. Concrete base patching and culvert pipe replacement will be conducted throughout the project limits.
September 16 to September 20:  Contractor will continue placing culvert pipes and will begin placing concrete masonry end walls at those new cross culverts. Base patching concrete, common excavation and placement of select crushed material and base aggregate dense will continue.
Traffic impacts: WIS 23 will be closed to through traffic from Townline Road to County VVV beginning Monday, Sept. 9 for a maximum of 35 working days.  Local & emergency vehicle access to homes & businesses will be maintained throughout the project.  Work will be conducted under flagging operations when the detour is not in place.
Detour: A signed detour will direct westbound WIS 23 traffic north on I-41 to southbound WIS 26 back to westbound  WIS 23. The detour will direct eastbound WIS 23 traffic north on WIS 26 to southbound I-41 back to eastbound WIS 23.